TermMeansMore
Working dayA day of the working week that is not a holiday, from the working calendar. Lengths, lags and slack count working days.Settings
Start and endThe two Jira date fields a bar runs between, both inclusive (by default Start date and Due date).Install
Parent / summaryAn epic, or a story with subtasks. Its bar spans its issues; its dates come from them.Read the chart
MilestoneA zero-length moment, drawn as a diamond: issues of type Milestone or the types an admin chose.Settings
DependencyA Jira issue link that orders two issues: the second waits for the first.Dependencies
Dependency typeWhich ends are tied: finish → start (the default), start → start, finish → finish, start → finish.Dependencies
LagWorking days added to a dependency: +2 leaves two days between; −1 lets the second start a day early.Dependencies
Auto-schedulingMoving an issue later pushes what waits for it, so dependencies hold. Nothing is pulled earlier.Dependencies
Critical pathThe chain of issues that decides the finish date: if one slips, the finish slips.Critical path
Slack (float)How many working days an issue can slip without moving the finish date. Zero on the critical path.Critical path
BaselineA saved copy of the plan's dates, to compare the plan with later.Baselines
VarianceHow many working days an issue ends later (or earlier) than in the baseline.Baselines
DraftDate changes kept on the chart, not yet in Jira, until you publish or discard them.Draft mode
OverduePast its end date and not done.Read the chart
OverbookedA person with two or more issues at the same time.Workload
Resolve overlapsMoving the later of a person's overlapping issues to their free time (levelling).Workload
Plan healthA score out of 100 for how sound the plan is, with what costs points.Plan health
ViewA saved filter with the way the chart looks, shared by the project and opened from a link.Views
PlanThe issues the chart shows: the project's, or those of a JQL filter.Views

Jira terms

Issue, epic, story, subtask, status, workflow step (transition), assignee, fix version (release), sprint and JQL mean what they mean in Jira; the chart reads them from Jira as they are.